Orchard Farm Evesham Road, Norton, EVESHAM, WR11 4TL
Wychavon District Council — appeal dismissed
- Outcome
- Dismissed
- Decision date
- 18 August 2025
- Authority
- Wychavon District Council
- Inspector
- Bromley N
- Procedure
- Written Representations
- Casework type
- Planning Appeal
- Type detail
- Unknown
- Development type
- Minor Dwellings
- Appellant
- Mr Steve Warner
- LPA reference
- W/25/00479/GPDQ
- ONS LPA code
- E07000238
- Jurisdiction
- Transferred
- Link status
- Not Linked
- Start date
- 20 May 2025
Summary AI
The inspector refused the appellant's application for a full award of costs against Wychavon District Council. The inspector found that the Council's approach to the application was not flawed or contrary to case law.
PDF text
Orchard Farm Evesham Road, Norton, EVESHAM, WR11 4TL — Wychavon District Council — Costs Decision Site visit made on 16 July 2025 by N Bromley BA (Hons) DipTP MRTPI an Inspector appointed by the Secretary of State Decision date: 18 August 2025 Costs application in relation to Appeal Ref: APP/H1840/W/25/3366009 Orchard Farm, Evesham Road, Norton, Evesham WR11 4TL • The application is made under the Town and Country Planning Act 1990, sections 78, 322 and Schedule 6, and the Local Government Act 1972, section 250(5). • The application is made by Mr Steve Warner for a full award of costs against Wychavon District Council. • The appeal was against a refusal to grant approval for “Prior Notification, Class Q for the Change of Use of Agricultural Building to two dwellings and associated works at Orchard Farm, Evesham Road, Norton, Evesham WR11 4TL.” Decision 1. The application for an award of costs is refused. Preliminary Matter 2. The appellant does not state whether a full or partial award is sought. Nonetheless, by reason of the information contained within the application, I have interpreted it as being one for a full award and have proceeded on that basis. Reasons 3. Parties in planning appeals normally meet their own expenses.
Orchard Farm Evesham Road, Norton, EVESHAM, WR11 4TL — Wychavon District Council — Costs Decision However, the Planning Practice Guidance (PPG) advises that costs may be awarded against a party who has behaved unreasonably and thereby caused the party applying for costs to incur unnecessary or wasted expense in the appeal process. 4. The appellant contends that the Council has incorrectly applied the GPDO and the PPG. It is also alleged that the Council ignored revisions made to the scheme and instead repeated the 2024 reason for refusal, and that they made no reference to the appeal decisions in Pinvin. 5. The Council’s delegated officer report (the officer report) provides background to the Council’s decision to refuse the application, and in my view the essence of the Council’s argument, that the scope of the building operations takes the scheme beyond Class Q, comes across clearly in the evidence. In particular, the officer report, and subsequent Statement of Case, goes into great detail, referring to the previous application at the site, relevant paragraphs of the PPG, the Hibbitt judgment, as well as other evidence provided by the appellant. 6. The PPG does say that internal works are not generally development.
Orchard Farm Evesham Road, Norton, EVESHAM, WR11 4TL — Wychavon District Council — Costs Decision However, it does not say that internal works must therefore be excluded from any assessment as to whether or not a scheme would comprise a conversion under the terms of Class Q. As such, I do not consider that the Council’s overall approach to be flawed https://www.gov.uk/planning-inspectorate
Orchard Farm Evesham Road, Norton, EVESHAM, WR11 4TL — Wychavon District Council — Costs Decision However, it does not say that internal works must therefore be excluded from any assessment as to whether or not a scheme would comprise a conversion under the terms of Class Q. As such, I do not consider that the Council’s overall approach to be flawed https://www.gov.uk/planning-inspectorate Costs Decision APP/H1840/W/25/3366009 nor contrary to case law. Indeed, my approach to the appeal is similar to the judgement of the Council. 7. While the Council do not refer to the Pinvin case, they provide a series of other appeal decisions, including a previous Class Q scheme at the appeal site. In any event, Class Q is highly fact and site sensitive, and decisions that are made are often dictated by a multitude of site-specific circumstances. They are also often finely balanced, as is the case here. As such, although I would have expected the Council to refer to the Pinvin case, it is unclear how this has caused unnecessary expense to the appellant in the appeal process. 8. Overall, for the above reasons, an appeal could not have been avoided and unreasonable behaviour resulting in unnecessary or wasted expense has not occurred. Accordingly, an award of costs is not warranted.
Orchard Farm Evesham Road, Norton, EVESHAM, WR11 4TL — Wychavon District Council — N Bromley INSPECTOR https://www.gov.uk/planning-inspectorate 2
Main issues and findings
Living conditions Against appellant ¶6
The inspector found that the PPG does not say that internal works must be excluded from any assessment of whether a scheme would comprise a conversion under Class Q.
Living conditions Against appellant ¶7
The inspector found that the Council's approach to the application was similar to the judgement of the Council, and that the lack of reference to the Pinvin case did not cause unnecessary expense to the appellant.
Living conditions Against appellant ¶8
The inspector found that an award of costs was not warranted because unreasonable behaviour resulting in unnecessary or wasted expense had not occurred.
Policies relied on
| Reference | Weight |
|---|---|
| Planning Practice Guidance (PPG) |
Moderate |
Site constraints from the Casework Database
Source
Decision letter, 2 pages, issued by the Planning Inspectorate on 18 August 2025 under the Open Government Licence.