Case 3330473

25 Southern Road, West End, SOUTHAMPTON, SO30 3ES

Eastleigh Borough Council — appeal dismissed

Outcome
Dismissed
Decision date
19 March 2024
Authority
Eastleigh Borough Council
Inspector
Redford R
Procedure
Written Representations
Casework type
Planning Appeal
Type detail
Planning Appeals - Full
Development type
Other minor developments
Appellant
Mr Joe Martin
LPA reference
H/23/95400
ONS LPA code
E07000086
Jurisdiction
Transferred
Link status
Not Linked
Start date
20 December 2023

Summary AI

The inspector refused to award costs to the applicant, stating that the council's decision was a matter of planning judgement and was fairly substantiated. The inspector also found that the council's position was not unreasonable and that the applicant's claim of unreasonable behaviour was not supported by the evidence.

Generated from the decision letter — check against the original before relying on it.

PDF text

Page 1 · Chunk 0 Costs Decision

25 Southern Road, West End, SOUTHAMPTON, SO30 3ES — Eastleigh Borough Council — Costs Decision Site visit made on 6 March 2024 by R J Redford MTCP MRTPI an Inspector appointed by the Secretary of State Decision date: 19 March 2024 Costs application in relation to Appeal Ref: APP/W1715/W/23/3330473 25 Southern Road, West End, Hampshire SO30 3ES • The application is made under the Town and Country Planning Act 1990, sections 78, 322 and Schedule 6, and the Local Government Act 1972, section 250(5). • The application is made by Mr J Martin for a full award of costs against Eastleigh Borough Council. • The appeal was against the refusal of planning permission for the erection of a front boundary fencing. Decision 1. The application for an award of costs is refused. Reasons 2. Parties in planning appeals normally meet their own expenses. However, the Planning Practice Guidance advises that costs may be awarded against a party who has behaved unreasonably and thereby caused the party applying for costs to incur unnecessary or wasted expense in the appeal process. 3.

Page 1 · Chunk 1 Costs Decision

25 Southern Road, West End, SOUTHAMPTON, SO30 3ES — Eastleigh Borough Council — Costs Decision The applicant considers that the Council have behaved unreasonably by over relying on comments from a technical officer, that the planning officer’s manager did not conduct a site visit, that the wider street scene had not been considered and that the guidance in the local Character Appraisal (CA) or the Quality Places Supplementary Planning Document (SPD) had not been referred to. 4. On review of the officer’s report, I find it provides a reasoned and proper judgement to support the Council’s decision. It shows a thorough assessment of the site and the potential effect of the scheme in the context of the street scene. There is not an over reliance on the technical officer’s comments, indeed the Council clearly state those comments were related to a linked application also currently under appeal (reference APP/W1715/W/23/3330474) and on review of the evidence before me I agree with this statement. It is not unreasonable for a manager to rely on the assessment of an area given by their officer, a qualified planning professional, rather than to undertake a separate site visit.

Page 1 · Chunk 2 Costs Decision

25 Southern Road, West End, SOUTHAMPTON, SO30 3ES — Eastleigh Borough Council — Costs Decision I am therefore satisfied the Council’s position in respect to the scheme is ultimately a matter of planning judgement and has been fairly substantiated. 5. I empathise with the applicant in relation to the ultimate decision differing from earlier indications made by the planning officer, prior to consultation with their manager. However, it is noted that within the email dated 10 August 2023 the planning officer states that ‘the proposal would be capable of officer support...’, it does not expressly state that the proposal is acceptable. Accordingly, I am https://www.gov.uk/planning-inspectorate

Page 1 · Chunk 3 Costs Decision

25 Southern Road, West End, SOUTHAMPTON, SO30 3ES — Eastleigh Borough Council — Costs Decision I am therefore satisfied the Council’s position in respect to the scheme is ultimately a matter of planning judgement and has been fairly substantiated. 5. I empathise with the applicant in relation to the ultimate decision differing from earlier indications made by the planning officer, prior to consultation with their manager. However, it is noted that within the email dated 10 August 2023 the planning officer states that ‘the proposal would be capable of officer support...’, it does not expressly state that the proposal is acceptable. Accordingly, I am https://www.gov.uk/planning-inspectorate

Page 2 · Chunk 4 Costs Decision

25 Southern Road, West End, SOUTHAMPTON, SO30 3ES — Eastleigh Borough Council — Costs Decision Appeal Decisions APP/W1715/W/23/3330473 satisfied that the change in direction is related to a better understanding of that proposed during the assessment of the scheme rather than a purposeful misdirection constituting in unreasonable behaviour. 6. Both the SPD and CA were referenced in the officer report’s policy section along with several other policies and documents. That there were not referenced in the main body of the report does not automatically mean they were disregarded. From the evidence before me I am satisfied the Council has shown discretion to both documents’ contents. As referenced in the appeal decision, there is clear guidance within the SPD in relation to higher frontage boundary treatments in areas predominated by lower frontage boundaries, and consideration of this point forms part of the Council’s case. 7. Consequently, for the reasons given above, unreasonable behaviour resulting in unnecessary or wasted expense has not occurred and an award of costs is not warranted.

Page 2 · Chunk 5 R J Redford

25 Southern Road, West End, SOUTHAMPTON, SO30 3ES — Eastleigh Borough Council — R J Redford INSPECTOR https://www.gov.uk/planning-inspectorate 2

Extracted from the decision letter PDF and shown in full, chunk by chunk.

Main issues and findings

Planning obligations
For appellant
¶3

The applicant claimed that the council had over-relied on comments from a technical officer and that the planning officer's manager did not conduct a site visit.

Planning obligations
Against appellant
¶4

The inspector found that the council's report provided a reasoned and proper judgement to support the council's decision, and that there was no over-reliance on technical officer's comments.

Planning obligations
For appellant
¶5

The applicant claimed that the council's manager had not conducted a site visit, but the inspector found that this was a matter of planning judgement and was not unreasonable.

Planning obligations
Against appellant
¶6

The inspector found that the council had shown discretion to the SPD and CA, and that the applicant's claim of unreasonable behaviour was not supported by the evidence.

Planning obligations
For appellant

The applicant claimed that the council had not referred to the guidance in the local Character Appraisal (CA) or the Quality Places Supplementary Planning Document (SPD), but the inspector found that the council's report did reference these documents.

Policies relied on

Reference Weight
Local Government Act 1972, section 250(5)
Limited
Town and Country Planning Act 1990, sections 78, 322 and Schedule 6
Limited
Planning Practice Guidance
Moderate
Local Character Appraisal (CA)
Limited
Quality Places Supplementary Planning Document (SPD)
Limited

Site constraints from the Casework Database

Conservation area
Green belt
Listed building setting
AONB
SSSI
Flooding an issue

Source

Decision letter, 2 pages, issued by the Planning Inspectorate on 19 March 2024 under the Open Government Licence.