231-233 High Road, Harrow , London , HA3 5EE
London Borough of Harrow — appeal allowed
- Outcome
- Allowed
- Decision date
- 7 August 2023
- Authority
- London Borough of Harrow
- Inspector
- Price A
- Procedure
- Written Representations
- Casework type
- Planning Appeal
- Type detail
- Planning Appeals - Full
- Development type
- Major dwellings
- Appellant
- W.E.Black Ltd
- LPA reference
- P/0877/21
- ONS LPA code
- E09000015
- Jurisdiction
- Transferred
- Link status
- Not Linked
- Start date
- 20 February 2023
Summary AI
The application for an award of costs against the Council of the London Borough of Harrow was refused. The Inspector found that the Council's behaviour was not unreasonable and did not result in unnecessary or wasted expense.
PDF text
231-233 High Road, Harrow , London , HA3 5EE — London Borough of Harrow — Costs Decision Site visit made on 28 June 2023 by A Price BSc MA MRTPI an Inspector appointed by the Secretary of State Decision date: 07 August 2023 Costs application in relation to Appeal Ref: APP/M5450/W/22/3294634 231-233 High Road, Harrow HA3 5EE • The application is made under the Town and Country Planning Act 1990, sections 78, 322 and Schedule 6, and the Local Government Act 1972, section 250(5). • The application is made by W E Black Ltd for a full award of costs against the Council of the London Borough of Harrow. • The appeal was against the refusal of planning permission for redevelopment to provide three to four storey building to create flats; parking; associated landscaping; refuse and cycle storage; closure of two existing vehicle accesses and creation of new vehicle access. Decision 1. The application for an award of costs is refused. Reasons 2. Parties in planning appeals normally meet their own expenses. However, the Planning Practice Guidance (PPG) advises that costs may be awarded against a party who has behaved unreasonably and thereby caused the party applying for costs to incur unnecessary or wasted expense in the appeal process. 3.
231-233 High Road, Harrow , London , HA3 5EE — London Borough of Harrow — Costs Decision The applicant submits that the Council has acted unreasonably in that there were delays in providing appeal documentation and that it failed to properly co- operate with the applicant, including in respect of the legal agreement. This is alleged to have resulted in wasted time and cost. 4. In respect of the delays in appeal procedures, I note that the Council acknowledge this. However, I am not of the view that this has necessarily resulted in any unnecessary or wasted expense in the appeal process. 5. In respect of the planning decision, I have noted each of the Council’s reasons for refusal, including reasons 2 and 3. These are specific and relevant to the application. They also clearly state the policies of the development plan which the proposal is considered to conflict with. These reasons, in my view, when taken together with the officer report, have been adequately substantiated, irrespective of any other decisions or proposals on the same site. 6. I acknowledge the frustration of the applicant in their attempts to communicate with the Council on various matters.
231-233 High Road, Harrow , London , HA3 5EE — London Borough of Harrow — Costs Decision However, I find nothing to suggest that a decision was not reached on the basis of the merits of the proposal, or that the Council would have come to any other decision overall if certain matters had been dealt with more efficiently. There is also no substantive evidence before me to demonstrate that the appellant incurred any additional expense as a result of these delays, and the decision was made on the basis of the refusal of planning permission rather than non-determination. https://www.gov.uk/planning-inspectorate
231-233 High Road, Harrow , London , HA3 5EE — London Borough of Harrow — Costs Decision However, I find nothing to suggest that a decision was not reached on the basis of the merits of the proposal, or that the Council would have come to any other decision overall if certain matters had been dealt with more efficiently. There is also no substantive evidence before me to demonstrate that the appellant incurred any additional expense as a result of these delays, and the decision was made on the basis of the refusal of planning permission rather than non-determination. https://www.gov.uk/planning-inspectorate Appeal Decision APP/M5450/W/22/3294634 7. It is evident from the main decision that I have disagreed with a number of the Council’s reasons for refusal. Nevertheless, I am satisfied that the Council’s overall determination of the application, and its reasoning, were credible and that it was entitled to reach the decision it did. 8. Therefore, unreasonable behaviour resulting in unnecessary or wasted expense has not occurred and an award of costs is not warranted. The Council set out a counter request for costs. However, there is insufficient evidence before me to substantiate this or to demonstrate how the applicant behaved unreasonably.
231-233 High Road, Harrow , London , HA3 5EE — London Borough of Harrow — A Price INSPECTOR https://www.gov.uk/planning-inspectorate 2
Main issues and findings
Living conditions For appellant ¶3
The applicant alleged that the Council acted unreasonably in providing appeal documentation and failed to co-operate properly, resulting in wasted time and cost.
Living conditions Against appellant ¶4
The Inspector noted the Council's acknowledgement of delays, but found that these did not necessarily result in unnecessary or wasted expense.
Living conditions Against appellant ¶6
The Inspector found that the decision was made on the basis of the refusal of planning permission, not non-determination, and there was no substantive evidence of additional expense.
Living conditions For appellant ¶3
The applicant alleged that the Council acted unreasonably in providing appeal documentation and failed to co-operate properly, resulting in wasted time and cost.
Site constraints from the Casework Database
Source
Decision letter, 2 pages, issued by the Planning Inspectorate on 7 August 2023 under the Open Government Licence.