30-32 Albany Street , London, NW1 4EA
London Borough of Camden — appeal allowed
- Outcome
- Allowed
- Decision date
- 19 July 2021
- Authority
- London Borough of Camden
- Inspector
- Caines A
- Procedure
- Written Representations
- Casework type
- Planning Appeal
- Type detail
- Planning Appeals - Full
- Development type
- Other minor developments
- Appellant
- Mr Keith Tillman (QHA Ltd)
- Agent
- MISHCON DE REYA
- LPA reference
- 2020/3800/P
- ONS LPA code
- E09000007
- Jurisdiction
- Transferred
- Link status
- Not Linked
- Start date
- 19 May 2021
Summary AI
The applicant sought costs against the Council for handling of the planning application, but the Inspector found no unreasonable behaviour resulting in unnecessary expense.
PDF text
30-32 Albany Street , London, NW1 4EA — London Borough of Camden — Costs Decision Site visit made on 13 July 2021 by A Caines BSc(Hons) MSc TP MRTPI an Inspector appointed by the Secretary of State Decision date: 19th July 2021 Costs application in relation to Appeal Ref: APP/X5210/W/21/3269211 30-32 Albany Street, London NW1 4EA • The application is made under the Town and Country Planning Act 1990, sections 78, 322 and Schedule 6, and the Local Government Act 1972, section 250(5). • The application is made by Mr Keith Tillman for a full award of costs against the Council of the London Borough of Camden. • The appeal was against the refusal of planning permission for enlargement of roof dormers and increased size of side extension. Decision 1. The application for an award of costs is refused. Reasons 2. Parties to a planning appeal are normally expected to bear their own costs, but costs can be awarded where the unreasonable behaviour of a party has caused another party to incur unnecessary or wasted expense in the appeal process. Briefly, the application for costs has been made in relation to the Council’s handling of the planning application.
30-32 Albany Street , London, NW1 4EA — London Borough of Camden — Costs Decision A fundamental concern is that the Council pre-judged the application on the basis of earlier pre-application advice and before the application was even validated. 3. However, the Planning Practice Guidance (PPG) is clear that costs cannot be claimed for the period during the determination of the planning application, even though all parties are expected to behave reasonably throughout the planning process. Whilst the PPG notes that behaviour and actions at the time of the planning application can be taken into account in the consideration of whether or not costs should be awarded, it first requires that an applicant demonstrate that a party has behaved unreasonably during the appeal and how any alleged unreasonable behaviour has resulted in unnecessary or wasted expense. 4. In my view, despite the appeal outcome, the Council has not demonstrated any unreasonable behaviour during the appeal, and the applicant has not demonstrated how any of the alleged unreasonable behaviour resulted in unnecessary or wasted expense during the appeal process. 5.
30-32 Albany Street , London, NW1 4EA — London Borough of Camden — Costs Decision I therefore find that unreasonable behaviour resulting in unnecessary or wasted expense, as described in the PPG, has not been demonstrated and therefore an award of costs is not justified.
30-32 Albany Street , London, NW1 4EA — London Borough of Camden — A Caines INSPECTOR https://www.gov.uk/planning-inspectorate
Main issues and findings
Planning obligations For appellant ¶3
The Planning Practice Guidance (PPG) states costs cannot be claimed for the period during the determination of the planning application, even if parties behave unreasonably.
Planning obligations Against appellant ¶4
The applicant did not demonstrate how any alleged unreasonable behaviour resulted in unnecessary or wasted expense during the appeal process.
Site constraints from the Casework Database
Source
Decision letter, 1 pages, issued by the Planning Inspectorate on 19 July 2021 under the Open Government Licence.